Posted on: May 4, 2023

Construction Updates and Schedules

More information is located HERE

April to June 15

• Prep work (water, sewer & highway) for Paving projects

 April – April 30

• Water ‐ Summer Line Upgrades

 April – May 15

• Sidewalk ‐ Main Street – West Side

• Sidewalk ‐ Main Street – East Side

• Sidewalk Town Pier – East Side

• Sidewalk Town Pier – West Side

• Agamont Lane Edge of Pavement Curbing

May 1 – May 15

• Water ‐ Hydrant Replacement Main St – East Side by Atlantic Ave

May 1 – May 30

• Sidewalk ‐ West Street – North Side by Bridge Street

• Paving – Otter Cliff Road

 May 15 – June 15

• Water ‐ Lower Ledgelawn Avenue Service Repair

• Sidewalk ‐ Main Street – East Side by Atlantic Ave

• Sidewalk ‐ Kennebec Street / Kennebec Place (if time permits)

May 15 – June 30

• Paving – Woodbury Road

• Paving – Devon Road

• Paving – Mountain, Rockwood, east Roads

June 15 – June 30

• Paving ‐ Conners Emerson School

July 1 – November 25

• Paving ‐ County Road

• Paving ‐ Bayview Drive (Hadley Pt to Rt3 – Head of Island side)

• Paving ‐ Indian Point Road (Town Landing Road to Oak Hill Road)

Fall – TBD

• Water ‐ Hydrant Replacement at 323

Main Street

October 26 – April 30, 2024

• Water – Complete Summer

Line Upgrades

Late November ‐ TBD

• Main Street Sewer, Water

and Stormwater

Improvements Project

 

* Typically, the pavement plants open up in early May, sometimes late April; and usually shut down mid‐November

 

 